Materials on site
In very broad terms, on construction projects, materials are sourced by the contractor and the client pays the contractor after they have been delivered to site.
Generally, the law considers that, unless the contract states otherwise, title (ownership) of materials passes from the contractor to the client at the time of delivery, irrespective of whether payment has been made. However, some forms of contract may state that ownership transfers upon payment. It is important therefore that the intention of the parties is clear and that these intentions cascade down through the contractual chain.
If delivered materials have been ‘affixed to the land’ or ‘incorporated into the building’, then ownership of the materials will transfer to the client even if they have not been paid for. If they have not been affixed to the land, that is, they can be easily removed without damage to themselves or their surroundings, but have been paid for, ownership only transfers to the client if the contractor themselves had title and so were in a position to transfer it.
This situation is complicated by the fact that the client generally only pays the main contractor at pre-agreed intervals, not every time something is delivered to site, and the complexity of the contractual chain means that the client may pay the main contractor, who pays a sub-contractors, who pays a supplier, and so on.
This can put the actual supplier at risk, for example, if the contractor, or any intermediate part of the supply chain defaults or becomes insolvent before payment is received. Depending on the terms of the contract, if the contractor has delivered the materials and the client has received them in good faith then ownership may be consider to have transferred to the client even if the supplier has not been paid.
A ‘retention of title’ clause (‘Romalpa clause’ or ‘reservation of title clause’) allows a supplier to retain ownership until specified conditions have been met, for example, until payment has been made. This can override the general principle that title passes on delivery and can give an unpaid supplier’s title priority over the client’s. However, there may be some risk to the client if they accept such clauses, for example, if the supplier becomes insolvent, and the receiver attempts to recover the materials. Standard fittings and stock items such as copper piping, electrical switches and ironmongery are items that might be removed from the site following the first sign of insolvency.
To be effective, the client must be aware of the retention of title. Furthermore, if the materials have been incorporated into the works they will no longer be capable of repossession.
Where the contract has terminated the supplier may be trespassing if they enter the site, and committing theft if they remove materials.
However, if the client subsequently installs materials to which they do not have title they may be guilty of 'wrongful interference', even if they are acting in good faith.
Before certifying payment for materials therefore, it is very important to be clear where the title lies. Consideration should also be given to whether materials are actually required at the time they are delivered. There may be circumstances in which it is useful to receive delivery in advance of the actual requirement (for example, so that goods can be secured if supply is short, or so that shipments can be combined to reduce costs), but this should not be used simply as a mechanism to improve the contractor’s or supplier’s cash flow.
It can sometimes be appropriate for the client to pay for items even though they remain ‘off-site’, for example, where a contractor has made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme
Paying for off-site goods or materials can put the client at risk, for example, if the contractor becomes insolvent and the items are then not delivered, even though payment has been made. There are a number of mechanisms for dealing with this risk, but none of them are completely fool proof. See Off site materials for more information.
NB: Project bank accounts (PBAs) have emerged as a means of enabling faster payments through the construction supply chain, with payments being made direct to subcontractors and suppliers as soon as 5 days from the due date.
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Bills of quantities.
- Bonds and guarantees.
- Construction contract.
- Construction inventory management.
- Contractor.
- Don’t run short of materials on your construction project
- Durability.
- Interim valuation.
- Lead times.
- Logistics management.
- Material handling.
- Materials.
- Off site materials.
- Project bank account.
- Site office.
- Site storage.
- Suction lifter.
- Retention of title.
- Testing construction materials.
- Vesting certificate.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.